TIP - >Negativ Resources
In the Open Standard
Hannes de BruyneMember for 21 years 2 months
- Created
- 0
- 1
0
Sometimes negativ resources are needed e.g. to make a material-balance (Excavation / Fill). It is not possible to write a negative figure into Budgeted Quantities BUT if you write a possitive figure and than changes the units per day to a negativ figure you will have a negativ resource!