How to calculate the real progress percentages
In the Open Standard
Francis Moyalan, PMP,PMI-SPMember for 21 years 8 months
- Created
- 7
- 4
0
I am working in a program which is having nearly 50k activities,
And I have to update the program every week and towards the month end give a report to the client a report on progress,
So what i am doing for getting the overall progress, is to assign prc to all the activities whose unit per time is 1, and take the tabular report of the earned value every month,
In case if an activity is not having any progress for a certain period and when it starts showing some progress then the previous percentages are getting changed,
Can anybody guide me in finding a realistic way to find the real progress,
Thanks ,
FMV
And I have to update the program every week and towards the month end give a report to the client a report on progress,
So what i am doing for getting the overall progress, is to assign prc to all the activities whose unit per time is 1, and take the tabular report of the earned value every month,
In case if an activity is not having any progress for a certain period and when it starts showing some progress then the previous percentages are getting changed,
Can anybody guide me in finding a realistic way to find the real progress,
Thanks ,
FMV
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?