RD = 0, but % Complete is not 100. How to resolve?
In the Open Standard
Alex RozenkevichMember for 22 years 1 month
- Created
- 8
- 3
0
Gentlemen,
Please voice your oppinion on the following:
For some activities mostly with short durations - f.e. 4 days, I have 90% progress, P3 shows RD = 0 and EF 1 day before the DD f.e. DD = 3-Feb-06, EF = 2-Feb-06, but it’s NOT ACTUAL!!! How can this be possible??
Even though 90% of 4 days is less than 12 hours and the planning unit of the schedule is days, I still believe it should not be 0 as 10% of the work still remains.. Even more incorrect to show EF non actual 1 day before DD, which means that the work should have been completed 1 day before independently of the remaining 10%.
Is there any cure to this disease?
P.S. I don’t want to break the link between RD and % as I will end up in a mess recalculating (or forecasting)RD manually.
Please voice your oppinion on the following:
For some activities mostly with short durations - f.e. 4 days, I have 90% progress, P3 shows RD = 0 and EF 1 day before the DD f.e. DD = 3-Feb-06, EF = 2-Feb-06, but it’s NOT ACTUAL!!! How can this be possible??
Even though 90% of 4 days is less than 12 hours and the planning unit of the schedule is days, I still believe it should not be 0 as 10% of the work still remains.. Even more incorrect to show EF non actual 1 day before DD, which means that the work should have been completed 1 day before independently of the remaining 10%.
Is there any cure to this disease?
P.S. I don’t want to break the link between RD and % as I will end up in a mess recalculating (or forecasting)RD manually.
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?