Budgeted Cost & Qty r showing Zero,,,pls. help to resolve
In the Open Standard
Muhammad Nasir HameedMember for 13 years 10 months
- Created
- 12
- 5
0
Dear All,
Hi,
I have prepared a plan in primavera 3.1, but facing a problem that Budgeted Cost and Qty are showing zero :(( , i have enter the units & prices in the resource directory, Units & Price Tape. Then assign that resources to the activities, but no use, i have no idea how to fix :((
please help to resolve this problem,,,,
Best regards,
12 replies
Oldest firstLog in or join to reply