S Curve not fixed
In the Open Standard
Steve WillisMember for 22 years 2 months
- Created
- 0
- 1
0
Hello all
I have been asked to run an S curve regarding Fabrication hours on site .
My problem is that this is a rolling changing curve for R & M work not a project with a fixed duration.
My hours change weekly from approved estimates either increasing or decreasing not extrawork .
I think i need to baseline on a weekly basis and run a new curve weekly or run an extra curve line showing increased work etc am i correct please help
thanks in advance
steve
I have been asked to run an S curve regarding Fabrication hours on site .
My problem is that this is a rolling changing curve for R & M work not a project with a fixed duration.
My hours change weekly from approved estimates either increasing or decreasing not extrawork .
I think i need to baseline on a weekly basis and run a new curve weekly or run an extra curve line showing increased work etc am i correct please help
thanks in advance
steve
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?