P3 fix utility

Daison Garvasis PekkattilMember for 20 years 4 months
Created
2
1
0
Anybody knows what is this files used for. I have seen it being used for recovering currept p3 project and though it took a while, it actually recovered the project which otherwise was unable to open.

2 replies

Oldest first
  1. 0
    Ronald Winter ·
    I am not sure that I understand your question. Are you looking for more information on the Primavera program called PFXW.EXE that ’fixes’ btrieve database relational file problems?

    Try running the program (found in the C:\P3WIN\P3PROGS\ directory)and click on the Help Button. There is a lot of information to be seen there. Good luck!
  2. 0
    Daison Garvasis Pekkattil ·
    I am not sure if that is the file I am refering to. I was told it comes with the utilites in the P3 CD. During one of our Turnaround, it really saved us!!! The project was not opening (it had almost 30,000 activities) and somebody run this utility and after sometime the file was recovered and it was running just fine after that.

    Thanks Ronald.