Export from Sure Trak to Excel

Naveen NayakMember for 23 years 2 months
Created
1
2
0
I have created a schedule containing 1000 activities on Sure Trak.
For the sake of this example if I have three levels to organise the activities namely Responsibility, Phase and System.
If I organise my schedule first by Responsibility, then by Phase and finally by System and show Total at top for Phase.
Can any one tell me if it is possible to export the information within these Total cells to Excel.

Naveen

1 reply

Oldest first
  1. 0
    Paul Harris ·
    Naveen

    I have not found a simple way.

    I usually copy & paste with the Activity Codes into Excel then run a Subtotal or a Pivot Table or a Vlookup to obtain the subtotals I require.

    Don’t forget to consider using Tools, Options, Defaults, Default clipboard format of Tab delimited, the help file will explain why.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au