Excel to P3

Benjamin NicomedesMember for 19 years 11 months
Created
27
4
0
Hello Planners:

Need your help and advice regarding conveting an Excel to P3 and vice versa?

Appreciate for any help.

Thanks.

27 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Benjamin,
    1. Set up a layout that contains the fields you want to import from Excel; this will be your template once open in Excel
    2. Enter a few activities and export the project to Lotus 123
    3. Open this .wk1 into Excel and enter the appropriate data
    4. Save the file, then import it into P3.
    That’s all
  2. 0
    Benjamin Nicomedes ·
    Thanks for trying to help but I can’t get it. Pls. elaborate more. Is there any other way without using Lotus 123?

    Thanks again.
  3. 0
    Fannie CHOW ·
    hi,

    I do it as below

    1. Export a template, select what field you need, to databass, dbf
    2. Open that dbf file and fill up the information.
    3.Save the file as check the "define"
    4.Import the file again.

    I think the trick is the define database field of excel.

    Hope it’s helpful

    Cheers
    Fannie
  4. 0
    Alexandre Faulx-Briole ·
    Benjamin,
    You do not need to have the spreadsheet Lotus 123 on your PC; MS Excel does open the wk1 files.
    Cheers
  5. 0
    Ronald Winter ·
    Actually, Excel does open WK1 files. Use File / Open and then change the file template by clicking on “Files of Type” dropdown at the bottom of the screen. Then you need to use the ‘elevator’ control to the right to scroll all the way down to the bottom of the list where it says, “Lotus 123 files.” Click there and you can now see and open the file. Goo luck!
  6. 0
    Mk Tse ·
    I prefer DBF format which Excel can open it also.
    There is some limitation on WK1 in Excel.
  7. 0
    Benjamin Nicomedes ·
    Still I could’nt get it. How could you make a wk1 files without using LOTUS 123? Could you please give an example of the format you are referring to? What is that dbf file?

    Sorry guys but am really confused.Thanks.
  8. 0
    Prabin Kumar ·
    Hi Benjamin,

    You can export any data in 4 format (i.e. - .PRN, .DBF, WK1 & WKS ).
    Except .PRN, all three can be open with Excel file.
    and you can import any data with DBF, WK1 and WKS format only.

    There is one more way to open and modify a p3 project in ms excel , i.e. by Ra->Sample->Excel folder. By this way you can fully access your project in excel , and can do some modification in your project from there.

    Thanks,

    Prabin Kumar
  9. 0
    Ronald Winter ·
    Perhaps we have been assuming too much. Here is the basics:

    Open your schedule. from the menu, select ’Tools’ / ’Project Utilities’ / ’Export’. Click on the export that sounds closest to what you want and then click on the ’Modify’ button. The ’Format’ tab will list the current file name and file type. The output is sent to your C:\P3WIN\P3OUT directory unless you state otherwise. Give it a try, you can’t hurt anything. Good luck!
  10. 0
    Hemanth Kumar ·
    if you have access to p3 installation cd
    get it
    explore
    find
    utilities folder
    open "excel" folder
    there are excel interfaces

    use it
    to get or set to p3 activities or whatever


  11. 0
    John Raper ·
    I think you have all missed one important issue here.

    Open P3;
    Export a layout that contains the essential fields to .WK1 or .DBF;
    Open that file (it’s in the P3OUT folder) in Excel;
    add the activities in the Excel file;
    (this is the important bit) save the Excel file IN .WK1 OR .DBF FORMAT - DO NOT SAVE AS .XLS;
    Import the .WK1 or .DBF file to P3.

    WK1 and DBF formats both work well, but there is a limit of 2400 activities when using WK1.

    Hope this helps
    John
  12. 0
    Ali Al-Rashed ·
    hi everybody,
    i have XL files can manage and control primavera file. u save alot of time and make ur work life easier .by using them.
    if u need it please contact me at my-email Ali.Alrashed@hotmail.com

    regards
    Ali
  13. 0
    Eric EVRARD ·
    Hello everybody,

    As John Raper said, there is a limit of 2400 activities with WK1 files.
    However, if you exceed 2400 acivities, you have to save 2 WK1 files with separated activities and 2 other WK1 files with the links.Once this is done save and close your WK1 files, if not no import will be possible.
    First import the 1st Activity WK1 files, then import the 1st Link WK1 file on an empty primavera layout.
    Do the same with the others activity & Link files on another primavera project.
    Close the second Primavera Project and from the 1st you make an import of the second project by using the transfert button in the import option window.
    I did it with 2950 activities and didn’t have any problems.
    Regards
  14. 0
    John Raper ·
    I implied, but didn’t state positively, that there is NO LIMIT to the number of activities if you use DBF files.
  15. 0
    Ruben Quintal ·
    hello everybody,

    i find its easy to import activity details from primavera to excel using import and P3 tools, but its kind of difficult trying to import a summarize data (eg. percent complete summarize by Floor Level).
    This import can be done very easily in P3 v5.
    Is there a way to do this in P3 v3.1?
    tnx,
    ben
  16. 0
    Rodel Marasigan ·
    Hi Ruben,

    I don’t quite understand your query. Do you mean displaying subtotal per floor level in P3v3.1 or import data from a project created into summary using Tools-> Project utilities-> Summarize?

    If you only wish to display the summary total on your P3v3.1 you can use Organize and on the Total column select Bottom or Top to display your subtotal. You don’t need to import it from excel because its automatic.

    If you required the percentage import from the created Project by P3 Project utilities summarize menu then use import/export facility from Tools-> Project Utilities-> Import… (I assume you are familiar import/export facilities)

    Regards,
    Rodel
  17. 0
    Amir Dadbakhsh ·
    Hi guys
    Be careful that Excel 2007 does not support saving in some old format such as WK1,WKS (this caused me a lot of problem ! if anyone has some excel interface which would be help to import & export data to p3, please email it for me dadbakhsh@yahoo.com)
    For your information, I paste some information which I found on http://blogs.msdn.com/
    The following formats cannot be opened or saved in Excel 2007:
    WK1 (1-2-3)
    WK4 (1-2-3)
    WJ3 (1-2-3 Japanese) (.wj3)
    WKS (1-2-3)
    WK3,(1-2-3)
    WK1,FMT(1-2-3)
    WJ2 (1-2-3 Japanese) (.wj2)
    WJ3, FJ3 (1-2-3 Japanese) (.wj3)
    DBF 2 (dBASE II)
    WQ1 (Quattro Pro/DOS)
    WK3,FM3(1-2-3)
    Microsoft Excel Chart (.xlc)
    WK1,ALL(1-2-3)
    WJ1 (1-2-3 Japanese) (.wj1)
    WKS (Works Japanese) (.wks)

    The following formats may be opened, but not saved to in Excel 2007:
    Microsoft Excel 2.1 Worksheet
    Microsoft Excel 2.1 Macro
    Microsoft Excel 3.0 Worksheet
    Microsoft Excel 3.0 Macro
    Microsoft Excel 4.0 Worksheet
    Microsoft Excel 4.0 Macro
    Microsoft Excel 97- Excel 2003 & 5.0/95 Workbook
    Microsoft Excel 4.0 Workbook
    DBF 3 (dBASE III)
    DBF 4 (dBASE IV)
  18. 0
    Eugene K ·
    amir, thx for info.
    moral of the story: not all upgrade may be good to us.
  19. 0
    Ruben Quintal ·
    rodel,

    im trying to find a way to automate the process of making weekly reports using P3 v3.1. By using summary function, that means that i have to input the data manually into excel to make a graphical presentation/report which is very time consuming. So, using export function in P3, using same format each import and linking the datas in excel, making the report is just a matter of 2 or 3 clicks of a mouse. The problem is that summarize datas cannot be imported into excel.any idea?

    Cheers,
    BEN
  20. 0
    Rodel Marasigan ·
    Ruben,

    I don’t have any problem exporting/ importing data from excel in P3v3.1.
    Follow this steps and it may help.

    1) Open your P3
    2) Select Tool-> Project Utilities-> Summarize..
    3) On the pop-up Summarize Projects Enter New Project name say: ABCD on Summary Project pull down box
    4) Click + on Source projects and select the project you want to summarize
    5) Click the Summarize by pull down box and select activity code to the level you want to summarize
    6) Set your data date and the rest items that you required and click Summarize button
    7) Open the New Project created say : ABCD
    8) Select Tool-> Project Utilities-> Export..
    9) Select Export File – Dbase – Schedule data or any format that you’re familiar and click Modify
    10) Add all the fields you wanted to export
    11) Click the Format Tab and Change the Name to new Filename that you wanted (note: dbf extension max of 9 characters only) and make sure the type is [.DBF] –III/IV
    12) Add sorting if required
    13) Click the Selection Tab if filter or selection is required
    14) Click run and select View on Screen
    15) The file created with .dbf extension by default is saved to P3OUT folder.
    16) Open your Excel program and on Open dialog box change the files of type to dbase files (*.dbf) and look for your exported file
    17) Update your data and save it to the same format
    18) Import updated database (.dbf) using P3 Tools-> Project Utilities-> Import…

    Your files should be updated. Let me know it you require further assistance.

    Regards,
    Rodel
  21. 0
    Ruben Quintal ·

    rodel,

    tnx a lot.


    ben
  22. 0
    Masood Ahmed Farooqi ·
    GOOD MORNING MY PROFESSIONAL MEMBER

    CAN YOU SEND ME THIS EXEL FILES FOR EXCELL TO P3

    REGARDS

    M.A. FAROOQI
  23. 0
    Amreshwar Shukla ·
    Hai Mr Masood Ahmed,

    Give me your Email address I will send the same to you.

    Regards,

    A.S.Shukla
    shukla@myrealbox.com


  24. 0
    Arvin Dayday ·
    IMPORTING DATA FROM EXCELL

    A. CREATING DATA IN MSEXCELL
    1.Open a New MsExcell file
    2.Create your data where column headers should match the P3 compatible abbreviation (required column headings are ACT-Activity ID, TITLE-Activity Description, OD-Original duration)
    3.DO NOT FORMAT THE CELLS of your excel file.
    4.Saves your File in a DB4 format.
    5.If prompter to save an active sheet only, click YES.
    6.If prompted to save in DB4 format only, click YES.
    7.CLOSE the file before importing to P3.

    B. IMPORTING EXCELL DATA IN P3
    1.Create a NEW P3 file
    2.To Import including ACTIVITY CODES VALUE, create first the ACTIVITY CODES
    3.Go to TOOLS, PROJECT UTILITIES, IMPORT
    4.Click ADD, and create a new REPORT
    5.Write the correct path of the DB4 file in the Enter path name and Input File cell (ex. File.dbf)
    6.Click OK to close and click RUN
    7.In the Output Option, point to Save in the ff. look file.
    8.Click OK
    9.Click CLOSE
    10.Click YES, when prompted to Rerun Current Filter.


    IMPORTING OR OPENING P3 DATA IN EXCELL

    A. CREATING DATA IN P3
    1.Create the P3 file
    2.Go to TOOLS, PROJECT UTILITIES, EXPORT
    3.Click ADD and create a new report file.
    4.Click Content tab and insert data in the list box you want to export to EXCELL or click ALL CURRENT to export the entire data of P3 to EXCELL.
    5.Click FORMAT tab, and create the DBF path and file name.
    6.Click RUN and point to Save to ff: Look File.
    7.Click OK to Close

    B.INSERTING EXPORTED P3 TO EXCELL
    1.Create a NEW file or OPEN an existing File.
    2.To insert the P3 file, go to DATA, IMPORT EXTERNAL DATA
    3.Click IMPORT DATA
    4.Search for the exported P3 file in DBF format and click OK
    5.Select a Cell, and click OK
  25. 0
    Claus Wellendorf ·
    Maybe a new problem:
    But how do you export the "activity type" for activities I have found the hammock definition under a heading "CON" part of "Constraints" export, but where is the WBS type the Start and finish Milestone types etc
  26. 0
    Ronald Winter ·
    The Matrix Report has the ability to report on activity types. Good luck!
  27. 0
    Mohamad Abdelsala ·

    Hi all, What if i am Using

    Hi all,

    What if i am Using Excel 2007 I can Export Data from P3.1 In DBF But i Cant import it Again Form Excel because Excel 2007 Cant Save in DBF format How Can i solve this Problem?

    Regards