Mandatory or Early constraint...
In the Open Standard
Nicolas BergerMember for 20 years 4 months
- Created
- 7
- 3
0
Hi everyone,
I’d like to know practically for what reason we should use Mandatory Contraints ?
I have always used Early constraints...
My sub-contractor has given me a schedule (1000 activities)with a least 50 Mandatory constraints...how to consider this knowing that those milestones are not contractual ?
What should I suggest to my Subcontractor as comments ?
Thanks by advance
I’d like to know practically for what reason we should use Mandatory Contraints ?
I have always used Early constraints...
My sub-contractor has given me a schedule (1000 activities)with a least 50 Mandatory constraints...how to consider this knowing that those milestones are not contractual ?
What should I suggest to my Subcontractor as comments ?
Thanks by advance
7 replies
Oldest firstLog in or join to reply