Resource Histogram finishes early. ?
In the Open Standard
Kevin MatthewsMember for 20 years 3 months
- Created
- 7
- 3
0
Hello,
I am using P3 3.1sp3 and have encountered a problem with the resource histogram finishing 4-5 months before project activities finish. I double checked the output with the resource profile/table output and all resources do seem to stop again 4-5 months before the activities?
The activties are a mix of hammocks and tasks and all have linear spread of hours, so they should be reporting hours to the end of the activities; not finishing 4-5 months before they are menat to.
Has anyone seen this before ?
Regards,
Kevin.
I am using P3 3.1sp3 and have encountered a problem with the resource histogram finishing 4-5 months before project activities finish. I double checked the output with the resource profile/table output and all resources do seem to stop again 4-5 months before the activities?
The activties are a mix of hammocks and tasks and all have linear spread of hours, so they should be reporting hours to the end of the activities; not finishing 4-5 months before they are menat to.
Has anyone seen this before ?
Regards,
Kevin.
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?