How to Get Rid Of "Neck" of Progress Bar
In the Open Standard
Praves SuppaMember for 20 years 5 months
- Created
- 7
- 1
0
Hello,
I had encountered a kind of clumsy work after update progress. Once pressed F9 some tasks were shown for neck bar after Data Date.
The tasks from which expressed were in the condition of
Remaining Duration < (Early Finish - Data Date)
and most of the tasks predecessor was linked and drived by FF with Lag relationship.
My Concerns are about being thousand adjusted of neck bars, that’s quite a nightmare in every single due time of progress report.
Anyone used to face this kind of experience please share an idea or solution, would be thankfulness.
Praves
I had encountered a kind of clumsy work after update progress. Once pressed F9 some tasks were shown for neck bar after Data Date.
The tasks from which expressed were in the condition of
Remaining Duration < (Early Finish - Data Date)
and most of the tasks predecessor was linked and drived by FF with Lag relationship.
My Concerns are about being thousand adjusted of neck bars, that’s quite a nightmare in every single due time of progress report.
Anyone used to face this kind of experience please share an idea or solution, would be thankfulness.
Praves
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?