Pressing F9 causes P3 to lock up

Seng FatsuraMember for 21 years 7 months
Created
5
1
0
Hello,

Can someone tell me what the F9 function does? I have a user who is trying to execute this function and P3 locks up on her. Thanks for any help/advice.

Seng

5 replies

Oldest first
  1. 0
    Fannie CHOW ·
    It’s because the logic link made a loop.

    Go "Tool Bar" >>> Click "Schedule" >>> A report will be generated and indicate what’s wrong at late part of it.

    Hope it’s useful.
  2. 0
    Praves Suppa ·
    Hello Seng,

    Could u pls show the pop-up message once it was locked? or What was message its shown?

    :-)

    Praves
  3. 0
    Seng Fatsura ·
    Hi Praves,

    Sorry so long. Been on hiatus. The message being shown is:

    Problem opening project file AG02TTl.P3, reason #88.

    Thanks for all your hellp.

    Seng
  4. 0
    Ronald Winter ·
    It is obvious that you have a bad data file. You need to run C:\P3WiIN\P3PROGS\PFWX.EXE and follow the instructions in the help file. Good luck!
  5. 0
    Ricky Sturdivant ·
    The PFWX.EXE also fixed and checked the files associated with this error: "NPB4ACT.P3 reason #88". The trouble was 1) selecting and "fill cell(s)" would not function, as well as 2) the delete actitivty would not function, until the application file "PFWX.EXE" was run.
    Thanks
    Ricky