Primavera 3.1, Error Activity is locked by another user

Ahmad Mustafa AzharMember for 18 years 8 months
Created
2
1
0

My Dear Friends,

In Primavera 3.1 1st time I am dealing with group project. when I am trying to update the activity in Main project or sub-project, for some activities it is giving an error " Current Activity is locked by another user". Can any body guide me to solve the current problem. 

Thanks

Ahmad

2 replies

Oldest first
  1. 0
    Steve Church ·

    Hi Ahmad, Try Deleting (or

    Hi Ahmad,

    Try Deleting (or renaming) the 1USERS50.P3 file.  You'll find it as one of the 24 Files for your project.  P3 will re-establish it next time you open your project.

  2. 0
    Ahmad Mustafa Azhar ·

    Thanks Mr.steve.I tried the

    Thanks Mr.steve.

    I tried the same but still the same error is appearing while updating some activities.

     

    Regards

    Ahmad