Update Target - New Activities
In the Open Standard
Natasha LordMember for 22 years 8 months
- Created
- 4
- 1
0
Apologies if this is a bit basic, I’ve only been using P3 "in anger" for 3mths and did the training about 2yrs ago now........
I have entered new activities in the current schedule and am trying to use the tools/project utilities/targets to update these into the target schedule.
However it does not seem to work.
I have made sure that both schedules are exclusive use. The target is closed when I try to do the update (otherwise it tells me it’s open). I click the for activities not in the target....and replace activity titles......
What am I missing? Do I have to go into the target and then do something else in there? I did notice that my target is now rescheduled from May to June 06 (same date as current), does this affect the target schedule, how do I stop that from happening?
Thanks!
I have entered new activities in the current schedule and am trying to use the tools/project utilities/targets to update these into the target schedule.
However it does not seem to work.
I have made sure that both schedules are exclusive use. The target is closed when I try to do the update (otherwise it tells me it’s open). I click the for activities not in the target....and replace activity titles......
What am I missing? Do I have to go into the target and then do something else in there? I did notice that my target is now rescheduled from May to June 06 (same date as current), does this affect the target schedule, how do I stop that from happening?
Thanks!
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?