Change WCB.1.100
In the Open Standard
George StewartMember for 23 years 11 months
- Created
- 1
- 1
0
WCB.1.100 >>> WCB1100 by Global change Command, too?
The easy way to do this is to export the program to Excel, highlight the I.D. column. Go to find and delete "." then import the complete programme back.
Sorry if this is not in detail but am on holiday and do not have a copy of P3 with me.
If you do not know how to do this repost and ask for advice from Forum members.
regards,
Geo
The easy way to do this is to export the program to Excel, highlight the I.D. column. Go to find and delete "." then import the complete programme back.
Sorry if this is not in detail but am on holiday and do not have a copy of P3 with me.
If you do not know how to do this repost and ask for advice from Forum members.
regards,
Geo
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?