P3 SCHEDULE VARIANCE
In the Open Standard
Trevor LyleMember for 22 years 3 months
- Created
- 2
- 2
0
I have reset the target for an existing schedule. I was expecting the Schedule Variance (SVQ) to be zero (0). However, substantial (negative) SV remains (Earned Value calculation is set to calculate against Target 1).
As the new target is effectively a copy of the current schedule, I cannot see why there should be any SV until there is a progress update and/or the data date moves.
I suspect it is something to do with original durations and actual durations (which are not the same) "spreading" the resource Budget Quantities over differnt periods.
Am I missing something and how would I eliminate SV after a project has been previously progressed?
Thanks
Trevor Lyle
As the new target is effectively a copy of the current schedule, I cannot see why there should be any SV until there is a progress update and/or the data date moves.
I suspect it is something to do with original durations and actual durations (which are not the same) "spreading" the resource Budget Quantities over differnt periods.
Am I missing something and how would I eliminate SV after a project has been previously progressed?
Thanks
Trevor Lyle
2 replies
Oldest firstLog in or join to reply