EPC schedule - split between Home Office and SITE
In the Open Standard
Carmen ArapeMember for 22 years 3 months
- Created
- 15
- 3
0
Hi Planners
Following the development of EPC schedule, you start at Home Office with a detailed Engineering and Procurement schedule. The construction section is just a rough idea of activities and a fixed time frame, for instance 12 months (that is the most important).
ONCE the project moves to Construction with Civil activities (do not take into consideration site preparation activities), you must develop a Construction schedule. The one that you used for some months at Home Office is no longer useful.
The EPC schedule is now split in two schedules with following structures and locations:
Engineering & procurement (E&P) : at Home Office
Construction : At Site
Links between E&P with Construction are now most important than before.
HOW CAN I KEEP MY EPC SCHEDULE?
Solutions
Keep EPC schedule at Home Office and update with input coming from Site. Unfortunately, I have tried this solution. Maintaining detailed construction schedules at home office is a nightmare.
Keep the EP schedule at Home Office and leave the detailed Construction schedule to Site Planners. Sounds good to me but How I can keep live the most important links such as: key drawings and Equipment&material arrival with construction activities.
Planners , How are you managing this situation.
Cheers,
carmen
Following the development of EPC schedule, you start at Home Office with a detailed Engineering and Procurement schedule. The construction section is just a rough idea of activities and a fixed time frame, for instance 12 months (that is the most important).
ONCE the project moves to Construction with Civil activities (do not take into consideration site preparation activities), you must develop a Construction schedule. The one that you used for some months at Home Office is no longer useful.
The EPC schedule is now split in two schedules with following structures and locations:
Engineering & procurement (E&P) : at Home Office
Construction : At Site
Links between E&P with Construction are now most important than before.
HOW CAN I KEEP MY EPC SCHEDULE?
Solutions
Keep EPC schedule at Home Office and update with input coming from Site. Unfortunately, I have tried this solution. Maintaining detailed construction schedules at home office is a nightmare.
Keep the EP schedule at Home Office and leave the detailed Construction schedule to Site Planners. Sounds good to me but How I can keep live the most important links such as: key drawings and Equipment&material arrival with construction activities.
Planners , How are you managing this situation.
Cheers,
carmen
15 replies
Oldest firstLog in or join to reply