Error in WBS-Bar ???
In the Open Standard
Hannes de BruyneMember for 21 years 2 months
- Created
- 7
- 5
0
Maybe somebody can help me?
My project is organized according to WBS. A WBS-Bar gives the summary of my WBS-Group. So far so good. If there is a Hammock within this group, still no problem.
BUT if this hammock is related to an activity with an ACTUAL Finish, my WBS-bar ends at my project-end and not at the end of my bars or hammocks.
is this right or an error in P3 ????
My project is organized according to WBS. A WBS-Bar gives the summary of my WBS-Group. So far so good. If there is a Hammock within this group, still no problem.
BUT if this hammock is related to an activity with an ACTUAL Finish, my WBS-bar ends at my project-end and not at the end of my bars or hammocks.
is this right or an error in P3 ????
7 replies
Oldest firstLog in or join to reply