Revision box of Graphics Reports

Julien LarguierMember for 20 years 1 month
Created
6
6
0
Hello !
I want to print Graphics with the following tool : "Tools/Graphics Reports/Ressource and Cost"
but I don’t find how to write anything in the Revision Box !!
Does somebody have a solution ?

Thanks
Julien

6 replies

Oldest first
  1. 0
    John Lawson ·
    Hi,

    - Try printing the charts to a pdf format.

    - Then edit the pdf.

    - You can make changes to the Rev. Box Titles, (copy and paste dont’t work in a pdf)

    Problem being it will need to be edited every time you update the project.

    I normally just use Resource/Cost Graphics click on the Tab called "Titles" and make a rev. remark in the "Rev. Title"

    Regards

    John
  2. 0
    Julien Larguier ·
    John,

    You can change the revision box in a pdf file ?

    ok for the second solution with the Revision Box Title ...

    Is there no solution directly in P3 ?

    Julien
  3. 0
    John Lawson ·
    Hi,

    1) You can change the revision box in a pdf file ?

    What you are actually doing is editing the pdf. Go into the pdf and click on a bit of the text and edit it, I used to just change the Revision Box Headers as never been able add in new items - (I have tried copy and past never seem to work).

    2) Second solution with the Revision Box Title, this works ...

    3) Is there no solution directly in P3 ?

    Not that I have found over the years, its a pity it is not like the Revision box when you print a schedule and you can change the Footers & Headers, that works well.

    As an alternative you could use the schedule format with the bars and have the Histogramme / S’Curve printed bellow, then you would be able to use the above revision box.

    Regards

    John
  4. 0
    Julien Larguier ·
    ok !

    your last alternative is what I was doing until now !
    but I wanted to do better with the appropriate tool ;-)

    Thanks for your help.

    Julien
  5. 0
    John Lawson ·
    Hi

    Just to correct myself - rather than print / edit the pdf, you can edit the "Primavera Look".

    To edit a pdf you will need additional software.

    John
  6. 0
    Julien Larguier ·
    John, thanks for your help !

    your solution is good :
    I edit my Graphic in Primavera Look
    I select the text "Date"
    I copy/paste it below in my revision box (using CtrlC/CtrlV or appropriate tool "Edit/copy - Edit/paste")
    I edit the new pasted text and I change it with my date : 06/09/07 for exemple


    Regards
    Julien






Log in or join to reply