Generate S-Curve & MPL
In the Open Standard
Redzuan SamsudinMember for 20 years 3 months
- Created
- 6
- 2
0
Good day
Q1 : How do I extract data from P3 (or let P3 generate) to create S-Curve.?
My usual method in MSP is listed below;
1 - VIEW | TASK USAGE
2 - Copy Work Hours distribution from day 1 to project complete sate.
3 - Paste in Excel & gnerate S-Curve (progress %) as Excel Chart.
Q2 : Can P3 do it per WBS/Activity Codes or discipline etc.?
Q3 : How do I generate Manpower Loading (unlevel) in P3.
MSP method:
1 - VIEW | REPORTS
2 - WORKLOAD | RESOURCE USAGE
3 - CROSSTAB
3.1 Row = Resources, Peak Unit
3.2 Column = 1, Days
All input very much appreciated.
Cheers
Q1 : How do I extract data from P3 (or let P3 generate) to create S-Curve.?
My usual method in MSP is listed below;
1 - VIEW | TASK USAGE
2 - Copy Work Hours distribution from day 1 to project complete sate.
3 - Paste in Excel & gnerate S-Curve (progress %) as Excel Chart.
Q2 : Can P3 do it per WBS/Activity Codes or discipline etc.?
Q3 : How do I generate Manpower Loading (unlevel) in P3.
MSP method:
1 - VIEW | REPORTS
2 - WORKLOAD | RESOURCE USAGE
3 - CROSSTAB
3.1 Row = Resources, Peak Unit
3.2 Column = 1, Days
All input very much appreciated.
Cheers
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?