How to Generate S Curve after resource Loading in P3???

Pranab Kumar DebMember for 19 years 8 months
Created
9
3
0
Dear Sir,
If some body can help me by noting the point wise approach to generating a S Curve after resource loading i would be Grateful.
regards
deb

9 replies

Oldest first
  1. 0
    Bijaya Bajracharya ·
    If you have resource loaded your activities, you have done the most time consuming part. In fact the S curve is already there now - and what you need to how to view it.

    Press the button "Resource/cost profile" which usually appear on to with bar chart icon on top. If you don’t see it, just go to View and then Ressource Profile.

    You will see the profile at the bottom of the screen. Click "Display" button and then choose curve. If you also want histogram, choose that as well.

    There are various filters and selection you can then apply depending on your need.

    Good luck
  2. 0
    Akin Adurosakin ·
    Try the link below; the result could be helpfull.

    http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=2&Top=26460.


    Regards,
    Akin Adurosakin
    Nigeria
  3. 0
    Bijaya Bajracharya ·
    It seems there is a need of SEARCH function in Planning Plannet.
  4. 0
    Bijaya Bajracharya ·
    I mean the SEARCH function should be functional.
  5. 0
    Pranab Kumar Deb ·
    thanks mr.bijaya and mr.Akin Adurosakin for the help
    regards
    deb
  6. 0
    Pranab Kumar Deb ·
    i fully agree with Bijaya , search option in planning planet will definitely help planners to have exactly the information that they are looking to else a lot of hard work by senior planners are wasted.
    regards
    deb
  7. 0
    David Moses ·
    Hi There;

    For search option in PP please check this:

    http://www.planningplanet.com/forum/forum_post.asp?Cat=3&Top=22552.

    I think it helps for the time being.

    Regards
  8. 0
    Pranab Kumar Deb ·
    thansk mr David it works perfectly well with google advanced search
    regards
    deb
  9. 0
    Mohd Anjum ·

    Can any body tell how to load

    Can any body tell how to load a resource and prepare resource loading schedule,

    indirect labour schedule and direct labour schedule?

    plz help me .if its long answer plz tell me the refrence.