bill of material

Syed Shahzad Hussain ShahMember for 20 years 1 month
Created
5
2
0
SIR,

How we can enter Bill of Material in P3.

SHAH

5 replies

Oldest first
  1. 0
    Charleston-Joseph Orbe ·
    Hi Syed,

    You can enter this in the resource with cost categories materials. So for each activities you will assign the particular materials.

    Cheers,

    Charlie
  2. 0
    Jose Frade ·
    Hello,

    Depending on the discipline it can be quite a job to include it in P3 - also depending on the project size.

    If referring to piping, Structural steel, Electrical, I&C, better to use a database (any) cause data manipulation will be enormeous that U will not have any time for the planning (revisions, field change notes, additionals, etc) - of course I’m thinking in Tones of piping, Kilometers of cables, hundreds 9at least) of instruments, valves etc - which U normaly have in Oil and gas works.

    BR
    JMFrade
  3. 0
    Tariq Usman ·
    hi shahzad,

    you can do this by using the resource catagory where you will find all the options.

    tariq

  4. 0
    Ashraf Alawady ·
    Agreed, use the cost catagory.
  5. 0
    Jose Frade ·
    Just to ilustrate a little bit better my thinking:
    PIPING - Normaly I never plan a deeper level then isometric:
    So imagine an activity ISO Prefrabrication Line XXXXXX

    Now the BOM
    21,2 m Pipe seamless 10" P22 ASME 36.10
    2 Un Elbow 10" LR BW P22
    1 un Red Tee BW 10/6" P22
    2.3 m Pipe Seamless 6" P22
    1 Un Elbow 6" LR BW P22

    And linking now with a FS the erection of this line with the following BOM

    6 Supports type X 10 "
    1 Valve 6" Globe kkkkkk
    + materials fabricated.

    Question: What do U want to achieve with BOM’s ?
    With this example about piping What would be the outcome beneficial for project planning?

    Then note: U have this BOM once Detail design for piping is finished for a certain line. U need to have a plan for the project at the begin with just a litle of Basic design.

    An example for steel structure would be even more worse with HEB profiles, xxx profiles, plates, bolts, nuts, etc.

    Project planning # Work preparation # invoicing quantities even though they comunicate each other.

    BR
    JMFrade

Log in or join to reply