adding RES BQ related to another RES
In the Open Standard
Gün GöksuMember for 21 years 6 months
- Created
- 2
- 3
0
hello.
I would like to add a resource as a percentage of another resource.
currently I use:
if RES EQ RES01
then RES EQ RES02
BQ EQ BQ * 0.2
then I reimport the original resources.
I have tried:
if RES EQ RES01
then RES AD RES02
BQ EQ BQ * 0.2
but the resource isnt transferred fromt the if clause to the then clause. thus I get a zero as BQ.
I have tried:
if RES EQ RES01
&A EQ BQ
then RES AD RES02
BQ EQ &A * 0.2
its a good idea. but temp values do not cross clauses I understand.
any way to transfer a BQ of a resource to another resource with global change?
yes I know I can export, change and reimport.
thank you.
Gün
I would like to add a resource as a percentage of another resource.
currently I use:
if RES EQ RES01
then RES EQ RES02
BQ EQ BQ * 0.2
then I reimport the original resources.
I have tried:
if RES EQ RES01
then RES AD RES02
BQ EQ BQ * 0.2
but the resource isnt transferred fromt the if clause to the then clause. thus I get a zero as BQ.
I have tried:
if RES EQ RES01
&A EQ BQ
then RES AD RES02
BQ EQ &A * 0.2
its a good idea. but temp values do not cross clauses I understand.
any way to transfer a BQ of a resource to another resource with global change?
yes I know I can export, change and reimport.
thank you.
Gün
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?