Physical progress

Alexandre Faulx-BrioleMember for 23 years 8 months
Created
2
1
0
Hello,
is there a way to enter physical progress in P3? or should I compute it the way it is explained in the thread http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=2&Top=0
Thanks for your answer

2 replies

Oldest first
  1. 0
    Paul Harris ·
    Alexandre

    I usually use the % Complete for physical progress.

    I then unlink all the auto cost rules and then I am able to enter actual hours and costs to date and estimates of hours and costs to go.

    I create three other Custom Data Items. % Duration, % Cost and % Hours which are calculated by Global Change.

    One can also use the % Complete (which represents the Physical % Complete) to calculate the cost and hours to complete from the Actual costs and hours, therefore using the actual progress to estimate the remaining progress.

    I create two baselines, one without progress and one that I auto status to give me the planned % complete.

    The article on my web site Practical Application of Earned Value Performance Measurement Using P3 shows some of the things one can achieve with P3. Look at the last 2 pages.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  2. 0
    Alexandre Faulx-Briole ·
    Thanks, Paul
    your answer is very useful for me
    Alexandre