Hammocks

Mark ArmstrongMember for 19 years 11 months
Created
7
4
0
Hi
i’m trying to setup a summary hammock that will allow me to roll up 5 successor activities. i’ve set the successors up as ff relationships as noted in the help files. I’m not to sure how to roll this up to a summary level though....

7 replies

Oldest first
  1. 0
    Ronald Winter ·
    Mark,

    You also have to set up the same 5 activities as Predecessors to the Hammock with Start-to-start relationships. Then re-calculate the CPM.

    The ‘roll-up’ occurs when you code the lower activities to be filtered-out ot the current view or report, leaving just the summary Hammock activity to represent them. Good luck!
  2. 0
    Umerfarook Deshmukh ·
    Yes Whatever Ronald suggested is the only way to solve your problem. If anyone else know any other way of Hammocking the activities please post reply.
  3. 0
    Mark Armstrong ·
    Thanks guys your advise has helped alot. i think i need to rethink how to set up my schedule. i’m now thinking hammocks aren’t the way to go with this particular issue.
  4. 0
    Eugene K ·
    hey guys, this is a question related to hammocks.

    i hv activties A1, A2, A3, B1, B2, B3
    and hammock HA covering A1, A2, A3
    and hammock HB covering B12, B2, B3

    question:
    in P3
    can i create hammock H covering HA and HB?
    or must i create H to cover A1, A2, A3, B1, B2, B3?
  5. 0
    Dayanidhi Dhandapany ·
    you can create Hammock H for covering HA and HB. it will show up the overall summary for the HA and HB.
  6. 0
    Reynaldo Y. Calayo Jr. ·
    hi guys!

    hi eugene......

    my suggestion....

    copy the file you are working on and experiment ....

    try what will happen ...........

    put the WHAT IF SCENARIOS...........

    have fun c",)
  7. 0
    Tahir Naseem PMP, CCE ·
    Hi eugene
    You can creat the Hammock activity in boath way. It is better in my opnion to use A1,a2,a3,b1,b2,b3 rather then HA, HB.
    regards

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?