hammocks

Ad BenMember for 19 years 10 months
Created
5
3
0
Ok First let me say If this has been asked I am sorry for reposting. But the search engine is not working so I have to ask

So, I have a project that the owner requires that we have hammocks for all subs. To show how long they will be onsite, i guess. The contract also includes bid items that are resorce loaded. so we get paid for how much we have done. So I made a hammock for the bid items that will show by % complete how much we can bill for.

With that being said. We have a hammock for us( The GC) that covers all sub-contractor hammocks & covers all bid item hammocks for billing.
In all of these hammock I have SS and FF on all activites.
I did this to show a moving hammock as we go along. What ever is the first activity that is under that hammock will be the one that gives it a AS and what ever is the last one that is done will give it the AF. When we are done it will be a perfect as-built sch. of the project.
All hammocks do not have a Pred. or Succ. they float on their own.
BUT the owner/scheduler is freaking out about it. Says I can’t have hammocks in hammock. I say BS

What do you think?

5 replies

Oldest first
  1. 0
    Ad Ben ·
    Once again I forgot that there is any other programs other than P3. This is what we are required to use. So my hammocks are being used in P3. Hope that helps out.
  2. 0
    Alex Wong ·
    Ad

    Lets see, what you have is a two level hammocks, summary of an summary. I do recall you can have a two tier hammocks. Will confirm @ home with my P3 3.1

    Alex
  3. 0
    Marsha Peterson ·
    Think about this... if you are not using the WBS coding structure for anything, then set up a WBS code for each sub... ELEC for all the electrical sub’s work..HVAC and so on. Code each activity in the WBS code area.

    Then generate an activity, with type WBS summary activity... with its WBS the same as your WBS code. Set one WBS type activity up for each, code it so that it appears at the top of your schedule... then when you calculate, it will show the start and finish showing the earliest in that code and finishing on the latest of that code... The WBS becomes a hammock...
  4. 0
    Ad Ben ·
    Marsh, Thanks
    I have never used WBS before. never have had to. I seem to learn what I have to with P3.
    I doubt that there is any problem with doing it the way you describe. That sounds like it would do the same thing. But it doesn’t answer what I asked.
    First I am required by the owner to hammock the subs tasks. His problem is that I include their hammock in ours since we are the GC and are responcible for what they do as well.
    He has a problem with a hammock in a hammock. I don’t see a problem, But I may be wrong. He can’t tell me why, just says that it is bad logic. I say it is just logic you have not seem before.
    Good New Logic.
    Thanks
  5. 0
    Alex Wong ·
    Marsha

    the only disadvantage using WBS is you cannot change the grouping order easly, WBS is great tool for a fix (Pretty Much) grouping. But because when we do schedule the environment changes, that make it very difficult to use. See posting in related to reassign WBS... you will see how many people having difficulties in P3 in WBS

    Cheers

    Alex