Hi, can you run a report in P3 to show the early & late dates for a project?

Alex

6 replies

Oldest first
  1. 0
    Alex Wong ·
    Yes
  2. 0
    Alex M ·
    Alex share the wealth?
    How do you do it?
  3. 0
    Andrew Podolny ·
    Hi

    Tools->Tabular Reports->Schedule...->SR-01 "Classic schedule report..."
  4. 0
    Alex Wong ·
    Thanks Andrew - and also you can use the graphic report to display it as well

    Alex
  5. 0
    Alex M ·
    Hi thanks very much, I ran the SR01 report, how do I respresent this in a grapical report?

    Alex
  6. 0
    Tahir Naseem PMP, CCE ·
    Dear
    Please run BC-02 report just
    Tool>graphical report>bar charts>bc-02
    change in contents tab against dates check box "both"
    Regards
    Tahir