Project / Activity Dates
In the Open Standard
Jonathan WardMember for 19 years 8 months
- Created
- 22
- 10
0
once again, another question i’m sure you will all find remarkably easy,, i have a project containing numerous activities all with different Early Start/Finish Dates, i have been asked to run some different scenarios in changing the project dates (we are governed by the arrival of an accomodation barge) i have tried changing the date on the Data Date line but this does not change the dates of all of the activities, is there a method of changing all of the activity dates in one hit to give figures for differnet scenarios?
many thanks
many thanks
22 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?