Progress Override

Elizabeth VMember for 19 years 11 months
Created
3
1
0
Can someone please tell me where to access the option for "Progress Override". I would also like to know the significance of this option, versus the logic override.

Thank you!

3 replies

Oldest first
  1. 0
    Karim Mounir ·
    Hi Elizabeth,

    You can checkout this address for more information about Retained Logic & Progress Override:
    http://www.pmicos.org/topics/aug2003.asp

    And You can choose the method of scheduling from:
    "Tools"-->"Schedule"-->"Options"

    Regards.
  2. 0
    Dayanidhi Dhandapany ·
    Hi Elizabeth,

    It is not logic override, that is retained logic, anyhow to access progress over ride, go to Tools->Schedule(Don’t press F9)->Options->look for progress override to check that option under the item when scheduling activities apply.

    remaining things look for the other post.
  3. 0
    Elizabeth V ·
    Thank you so much! That article is very informative.