RA Excel Files Help ???

David MosesMember for 21 years 11 months
Created
10
4
0
Dear All,

Now I am using Excel 2007 on my new desktop.

But I could not open/use those excel RA Files (ACTIVITY.XLS and PROJECT.XLS) to export and import.

When I try to open those excel files this messege comes "could not load an object because it is not available in this machine" !!!

What should I do? Please help me !!!

Regards

10 replies

Oldest first
  1. 0
    David Moses ·
    By the way Operating System is Windows XP Professional on my desktop.
  2. 0
    Jorge Santos ·
    hi mr. david
    i’ve got a problem same as yours, if u found d solution could u share it to me...tnx..


    regards
  3. 0
    Alexandre Faulx-Briole ·
    Hi all,
    switch back to MS Excel Xp or 2003!
    Alexandre
  4. 0
    Pranab Kumar Deb ·
    ya that is the only way , go back to excel 2003
  5. 0
    David Moses ·
    Hi There,

    Are you serious? I mean going back to excel 2003? If it is the only solution OK. But what is causing this. Have any idea?

    Regards
  6. 0
    David Moses ·
    Hi There,

    Another problem is that excel 2007 is not allowing to save the files as wk1 or dbf. So that exporting/importing with excel 2007 seems impossible. Do have any idea for this?

    Regards
  7. 0
    Pranab Kumar Deb ·
    same reason - excel 2007 doesnt support excel older than 1997-2003
  8. 0
    Alexandre Faulx-Briole ·
    Hello all,
    as a matter of fact, one should not use MS Office 2007, except if MSO is the only application software on the computer;
    MSO 2007 is denying any working possibility to any other apps on the pc
    MSO 2007 is 110% proprietary, it is not even possible to save files under an older MS file format!
    ergo, do not use MSO 2007
    Alexandre
  9. 0
    Hannes de Bruyne ·
    open dbf in access copy to excel, than back to access and save as dbf.

    Hannes
  10. 0
    Taqi Hasan ·
    Reinstall Excel 2003. you can retain both excel 2003 and 2007 on the same OS. Use 2003 for export-import and 2007 for the rest. I find MS Excel 2007 much superior to its predecessors. Alternatively, consider using Open Office (freeware) for dbf/wk1 formats.