Network Diagram

Sajid BalmaMember for 19 years 4 months
Created
11
3
0
Hi All
I am a newbie in planning. I have developed a WBS and activity codes for my project. Based on these parameters I have lited down some 600 activities for my schedule. Now, I want to define a network diagram. But, I feel a lot of problems linking activities. I just lost my tracks while linking those activities. Any suggestions or tips and tricks would be highly appreciated.

Balma

11 replies

Oldest first
  1. 0
    Sajid Balma ·
    Forgot to mention that I am on p3.
  2. 0
    A D ·
    Instead of jotting down 600 activities in P3 and then linking them, the best way to do is to first create a activtity cycle. Say a cycle of 30 activities for one floor and then repeating these activties. You can store that as fragnet.

    Then you can link floor-to-floor activities.

    Same you can repeat for structures / MEP / Cladding and other finishing items.

    Cheers,

    Raviraj
  3. 0
    Ashraf Jahangeer ·
    Ravi,

    Excellent idea...can you explain a bit more on using Fragnet.

    In fact I have never used it, I used excel for repetitive type of activities and then import these files into P3 project.

    Regards,

    Ashraf
  4. 0
    Sajid Balma ·
    Hi Ravi
    Excellent idea!!!!!!! The only thing I need to do is to re-develop my project using fragnets. But, correct me if I am wrong, I need to change the activity codes for repeated activities each time I retrieve a fragnet. I mean, activity codes contain location information which will be copied exactly the way I have in fragnet.
  5. 0
    A D ·
    Hi Ashraf / Sajid,

    I have a good paper on using fragnets.

    send me a mail on ravirajab@yahoo.co.in

    Cheers,

    Raviraj
  6. 0
    Ulysses Garcia ·
    Hi,

    i suggest that you need to turn your back from p3 into primavera P5 . your problem will be solve as easy as feeding chicken.
    In a complicated world using p3 fragnet it will be more convinient to use MMD methology management then link it to primavera P5 or to make onself easy use excel . imp/ex.
  7. 0
    Sajid Balma ·
    Hi Ravi
    Thanks for your email with some valuable infomation on FRAGNETS.
  8. 0
    A D ·
    THe most easy way i do is to have (Works better than fragnet):

    copy the cycle time (group of activity with relationships defined). Note: In the cycle time, keep only the last three digits in the activity field.

    Filter -> No activities

    It will ask for three options for renaming activities:
    - Rename all
    - Prefix / sufix
    - Auto-increment

    Click on prefix and enter OK.

    Type in the activity ID required

    and then filter it for all activities.

    Re-organize it.

    Thats it.

    This is most fast and easy way for adding activities.

    Cheers,

    Raviraj A Bhedase
  9. 0
    Pranab Kumar Deb ·
    Hello Raviraj,
    Can you explain what is the motive of keeping the last 3 digits alone in the activity field.
    regards
    deb
  10. 0
    A D ·
    These are numbers allocated for the unique activity in the cycle time.

    Say for procurement i allocate ID’s like 101, 103, 105, 107

    For Engg., 001, 003, 005, 007

    For Installation, 201, 203, 205

    First seven alphabets/nos. can be used with upper level of WBS/activity codes. This will help you to identify/filter activities much better.

    This is my practice again. You can change it as you want. You can have 4 nos also, but sometimes you struggle with acivity ID , as only 10 digits can be allocated for creating avtivity ID (In p3.1 at least)

    Cheers,

    Raviraj A Bhedase
  11. 0
    Mike Testro ·

    Hi Lothar Good sales pitch

    Hi Lothar

    Good sales pitch even if the topic was 5 years old.

    Best regards

    Mike Testro