PERT View

Moutaz AldeibMember for 22 years 9 months
Created
4
1
0
Dear All,

Can anybody tell me what is the benefit of using PERT view in program contains more than 1000 activities linked?

Thanks in advance

4 replies

Oldest first
  1. 0
    Mk Tse ·
    I filter the concern activities on PERT to check the relationship
  2. 0
    Alex Wong ·
    Logic and CPM analysis is easier in PERT chart

  3. 0
    Moutaz Aldeib ·
    Thanks every body but I think it is not so easy to use PERT in CPM analysis.

    Thanks alot.

    Moutaz
  4. 0
    John Raper ·
    Moutaz

    It is easy, but you need to make use of the tools available in P3.
    Try filtering for critical activities (TF<1) to reduce the number of activities in view.
    Use the ’Trace Logic’ window in Pert View. This shows a small window at the bottom of the screen with the selected activity in the centre. You can click on the activities either side to trace through the logic.

    I agree 1000+ activities is hard to see on the screen!

    Good luck
    John