Resources on Summary Bars

David MilburnMember for 23 years 7 months
Created
2
1
0
I’m new to P3 so please go gentle !
Is it possible to assign resources to summary bars?
Id like to be able to allocate some staff resources to the overall project rather than specific activities. Is this possible, i cant find a way to do it.

thanks in advance

2 replies

Oldest first
  1. 0
    Gün Göksu ·
    try and use a hammock activity. start-start to first activity in schedule, finish-finish to last activity in schedule. activity type: hammock. it is good practice to link the start and ends to milestones. Gün.
  2. 0
    Mohamed Ibrahim ·
    David,

    The easy way is to insert an activity and change the type to WBS instead of task and then schedule, there is no need for any links and this will be similar to the summary bar and you can assign resources to this activity with your lag and duration for each resource as normal.


    Kind Regards
    Mohamed