Activities link

Amr DiabMember for 19 years 8 months
Created
1
1
0
hello

I have a question concerning the link between the 2 floors containning the same activities, do i have to link each similar activities or just link the 2 floors.

also i hade a comment on a programme i m working on it (EPC) that consist of 1267 activities and contains 25 critical activities... tell me if there is a problem in that??!!!
the comments maker mentioned that its an record !!!!

last please tell me how to impose project end date

please tell me your opinion

1 reply

Oldest first
  1. 0
    Brennan Westworth ·


    1/ you need to understand the logic between the activities, in a multi story building, no matter how far ahead your M & E is they will never overtake your structure (very basic example used there).

    2/ 2% critical activities... without knowing the details of the schedule I wouldnt say this is excessive. Was the comment that there were too few or too many activities?

    There is a post here somewhere about % of critical activities with some good comments.

    3/ the way i usually impose an end date is to apply a late constraint to contractural completion dates (PC or completion of separable portions) this way you can use negative float to analyise the real float of your activity chains and see where acceleration is required to meet programme.

Log in or join to reply