some questions...

Amr DiabMember for 19 years 8 months
Created
2
1
0
Dear ALL

I have some questions:

1: if there is a different between leaving the project end date open or impose the project finish date in order to determine the critical path?

2: Could (Punch listing & Prepare for Handover)activity of every floor have LF = Project End Date?

3: The program I m working on consist that every floor is like an independent small project (1st&2nd fix) therefore even if the project showed delays, not all activities became critical even if they are delayed... I think it’s normal

Please advise.

Amr

2 replies

Oldest first
  1. 0
    Mohamed Basheer ·
    Dear Mr.Amr

    Even though the question is not very clear to me , let me try my understanding of ur Question.

    1.If you define the must finish date : every activity goes beyond will be critical. If you leave open the longest path will be critical.

    2.Punch list of All final activities will have LF as project finish but not the activities having predecessors. to explain... if you have puch list on the surface evenness of wall it has to done before the final painting is done not till the project complete.

    3.No answr
  2. 0
    Kishor Raj ·
    your second question depends on the requirement of client.ie if they have a handover schedule then you have to constrain that floors to the agreed handover dates. otherwise it will show a float and you dont have to worry about it since it is a float available for the contractor to schedule his resources accordingly.

    3. First fix and second fix will be linked to the final fixes and the final testing and commissioning of the rooms. First fix wall services obviously will affect the finishes. So better connect it to the plaster.

    I beleieve this will help you

    regs

    Kishor

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?