some questions...
In the Open Standard
Amr DiabMember for 19 years 8 months
- Created
- 2
- 1
0
Dear ALL
I have some questions:
1: if there is a different between leaving the project end date open or impose the project finish date in order to determine the critical path?
2: Could (Punch listing & Prepare for Handover)activity of every floor have LF = Project End Date?
3: The program I m working on consist that every floor is like an independent small project (1st&2nd fix) therefore even if the project showed delays, not all activities became critical even if they are delayed... I think it’s normal
Please advise.
Amr
I have some questions:
1: if there is a different between leaving the project end date open or impose the project finish date in order to determine the critical path?
2: Could (Punch listing & Prepare for Handover)activity of every floor have LF = Project End Date?
3: The program I m working on consist that every floor is like an independent small project (1st&2nd fix) therefore even if the project showed delays, not all activities became critical even if they are delayed... I think it’s normal
Please advise.
Amr
2 replies
Oldest firstLog in or join to reply