P5 Questions
In the Open Standard
Neil BradyMember for 19 years 9 months
- Created
- 0
- 2
0
Guys
Looking for a bit of your collective expertise here.
I have a couple of questions as follows.
1. Detailed Summary Charts. Is it possible to have a summary bar that shows rolled up progress / manhours etc from lower levels ? I can get it to show a summary bar, but I can’t seem to have it show any summarised information.
2.More of a query regarding variations. How is this done with in the industry using P5 ? We are having problems coming up with a suitable strategy.
Take the variation hours and add them to the baselined hours - Loose any sense of reporting on what they were for.
Take the variations and add them in as seperate activities -fine in principle, we retain visability and reportability but as we time write against these activities it could be messy.
Any thoughts on how we might approach this ?
As always your advice is greatly appreciated !!
Cheers
Neil
Looking for a bit of your collective expertise here.
I have a couple of questions as follows.
1. Detailed Summary Charts. Is it possible to have a summary bar that shows rolled up progress / manhours etc from lower levels ? I can get it to show a summary bar, but I can’t seem to have it show any summarised information.
2.More of a query regarding variations. How is this done with in the industry using P5 ? We are having problems coming up with a suitable strategy.
Take the variation hours and add them to the baselined hours - Loose any sense of reporting on what they were for.
Take the variations and add them in as seperate activities -fine in principle, we retain visability and reportability but as we time write against these activities it could be messy.
Any thoughts on how we might approach this ?
As always your advice is greatly appreciated !!
Cheers
Neil
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?