export&import exel to P3

Drajat PermanaMember for 20 years 3 months
Created
2
2
0
I try to copy schedule from microsoft project to P3 by

using export/import.

but always failed.

please give me advise for this matter to me. step to step by using export and import tool P3

2 replies

Oldest first
  1. 0
    Eva Martin ·
    export and import process from MS Project to P3 has still some bugs, you will be surprised to see everything imported to P3 but when you time analyzed the programme some activites are not moving according to their logic or relationship.

    It would save you time if ’copy and paste’ the activity ID, Description and Duration rather than retyping it manually onto P3. (and) The rest has to be rebuild on P3 (e.g. link and resources)
  2. 0
    Paul Harris ·
    There is a paper on my web site which explains this process.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au