labour count by discipline

Jonathan WardMember for 19 years 8 months
Created
3
2
0
is there a method of finding the number of men per discipline in any set time period?
i.e. i would like to know the number of painters working on my project during the week beginning 9th April ending 15th?
this is for a histogram that i produce away from P3
- many thanks

3 replies

Oldest first
  1. 0
    Mark Chapman ·
    Create a filter with resource equals painters then go to View and Resource Table. Use the display option to modify personal options like time intervals of 1 week.
  2. 0
    Jonathan Ward ·
    thats great, thanks for your help
  3. 0
    Bijaya Bajracharya ·
    To see the resource table, there is no need to use filter. In fact even when you use a filter, the table will still show all the resources. But that should not be problem- just look at the row (resource) you are intrested in.