character count in Activity Description

Jonathan WardMember for 19 years 9 months
Created
9
20
0
hello,
i bet this question has been asked before,,, are there any cheats for increasing the 40 character limit?
many thanks
jon

9 replies

Oldest first
  1. 0
    Pranab Kumar Deb ·
    IF U ARE THAT SURE SEARCH WITH GOOGLE ADVANCED SEARCH OPTION PUTTING WWW.PLANNINGPLANET.COM ON THE DOMAIN NAME.
    REGARDS
    DEB
  2. 0
    Jonathan Ward ·
    ,, it was a question,, not a STATEMENT!!
  3. 0
    Steven Oliver ·
    For extended descriptions, or other notes, use the log text fields
  4. 0
    Jonathan Ward ·
    Thank you Steven, i have used the insert function and it does what i require
  5. 0
    Mark Chapman ·
    Jon,

    Can you explain what you mean? What version are you running?

    Cheers,

    Mark
  6. 0
    Jonathan Ward ·
    hello Mark,
    i’n running 3.1, all i wanted to know is if there is a method of expanding the length of the Activity Description, at the moment i am limited to 40 characters
    many thanks
    jon
  7. 0
    Ife Olyke ·
    Hi Jon,

    Well..This is one of the limitations of P3 ver 3.1. You are limited to only 48 characters (including spaces). You can use the format =>column function to adjust the activity description column though, but not the character length.. By the way, I am interested in knowing how you used the insert function to achieve that..

    Cheers

    Ifeanyi
  8. 0
    Pranab Kumar Deb ·
    Dear Jonathan,
    Even i searched for it in the forum thats why advised u the same , but without results do let me know if u could get in more than 48 characters.
    regards
    deb
  9. 0
    Bijaya Bajracharya ·
    Use Custom Data Item (Data/Custom Data Item) and create a new field say AFD for Activity Further Description. This should be Character (C) type of data and now you can add 20 more characters on top of 48 in the activity description. Just select your new custom data item to be shown next to your activity description in the columns. It works just like logs.