cost control

Forat FarisMember for 20 years 2 months
Created
1
2
0
dear all
when some activities canceled in the project ...I input the pc%=100%..
but cost report which i generate in p3 will not reflect the real picture .
HOW WE CAN REFLECT REAL COST SITUATION IN P3?
THANKS

1 reply

Oldest first
  1. 0
    Ife Olyke ·
    Hi Forat,

    I will not input pc% = 100% for an activity if it’s cancelled. I’d rather create a planning level for cancelled activities and apply it to activities i want to cancel. Then in the cost report format, I will add a selection criteria to exclude all cancelled acitivities. Hope this helps..Maybe someone else will have a better idea. Cheers..

    Ifeanyi

Log in or join to reply