P3 3.1 look ahead schedule

Tim HortonMember for 19 years 5 months
Created
1
1
0
When I was printing 3 week look ahead schedule my background colour on the sheet was yellow, how can I remove that yellow colour background in P3 3.1?

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Tim,

    Check if Progress Spotlight is on. Select View-> Progress Spotlight and uncheck or click progress spotlight icon.

    HTH,
    Rodel