RETAINED LOGIC or PROGRESS OVERRIDE

Ashraf JahangeerMember for 19 years 5 months
Created
3
2
0
For updating the schedule in general and out-of-sequencework in particular which option for schedule calculation in P3 3.1 is preferable - RETAINED LOGIC or PROGRESS OVERRIDE . What merits/demerits are associated with both these calculation methods?

3 replies

Oldest first
  1. 0
    Arvin Dayday ·
    ashraf,

    kindly open and read this link.....http://www.pmicos.org/topics/aug2003.asp

    regards

    arvin
  2. 0
    Ife Olyke ·
    Arvin, that was a very interesting article.

    is it possible to filter only out-of-sequence activities?
  3. 0
    Amreshwar Shukla ·
    Dear Olike,

    There is no way by which u can filter the out-of-sequence activities in P3. But u can look the report generated during the scheduling itself which will inform u about all out-of sequence activites.
    If u are more interested u can look other software like Schedule Analyzer.-http://www.ronwinterconsulting.com/sa_main.htm

    Regards,
    A.S.SHUKLA
    Shukla@myrealbox.com

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?