Update Progress P3 3.1

Paul WaterMember for 19 years 4 months
Created
4
2
0
When I update my schedule, I updated my schedule manually for 50 % 100 % completed activities. But when I click the update progress the activities not yet even started show 5 % 10 % completed. Any friend may please guide?

4 replies

Oldest first
  1. 0
    Arvin Dayday ·
    Because

    Update progress is an automatic way of updating a project. Meaning P3 quickly estimates activity dates, percent complete amounts, and remaining durations as of the new data date you specified by dragging the data-date line or by using the Progress Spotlight feature.
  2. 0
    Christian Adrian De Vera ·
    Agree with Arvin.. if you’re updating your program just put all the actuals and press F9..
  3. 0
    Anoon Iimos ·
    some people are claiming that P3 is becoming obsolete while others still don’t have a clue! (including me);

    P3 is using Duration; Resource Units and Costs

    in updating P3 by just putting actuals, make sure you chose Duration

    when you’re using Resources Units (which i supposed seldom used or never), make sure you got all the quantities!

    when using Cost! I’m sure you’ll never get what you want!
  4. 0
    Amreshwar Shukla ·
    Dear Paul,
    When you do automatic update, then P3 assume that everything are moving as per plan and update every activity as per initial base plan. If there are any deviations then update as mentioned by Arvin and Anoon.
    Regards