Global change for Lags...

Nicolas BergerMember for 20 years 4 months
Created
2
1
0
We are under migration from a schedule planned in days to a schedule by hours.

We changed everything except lags.
How can we change it by using a global change ?

2 replies

Oldest first
  1. 0
    Andrew Podolny ·
    Use Import / Export (Activity ID, Logs) instead of Global Change.
    Regards
    Andrew
  2. 0
    Nicolas Berger ·
    Yes I know but we were wondering if it might be possible using the global change...