Problem in fliter running

Sinan FahmiMember for 19 years 10 months
Created
4
4
0
Hi my freinds,
i faced a problem when i am going to run filter i got a message "proj environment is too long" and before that the same filter was running without any problem.

i need your support in the case
thanks

4 replies

Oldest first
  1. 0
    Ashraf Jahangeer ·

    Hi,

    Is your project in sub-sub-sub directory.

    Try to meve it up and then try running the filter.

    Regards,

    Ashraf

  2. 0
    Sinan Fahmi ·
    thank you my freind
    it working now
    thak again

  3. 0
    Tom Howard ·
    As you found out, it is related to the length of characters in the file path. Moving it up the hierarchy will solve it, however you may have a programme directly in the C:Drive called "thisisaverylongandstupidlynamedprogrammewithlotsofcharactersrevision1draftprogramme" that displays a similar problem
  4. 0
    Steven Oliver ·
    Not in P3, you wouldnt.