running P3 on other than btrieve6.15
In the Open Standard
Gün GöksuMember for 21 years 6 months
- Created
- 6
- 4
0
Hi,
I know P3 runs on Btrieve 6.15.
is it possible to switch the database component to something else? like an updated modern pervasive or sql database?
I am running on some performance & stability issues and would love to get on to some other database engine.
before you ask, the client is locked on P3 v3.1 and won’t upgrade to P6.
Thank you.
I know P3 runs on Btrieve 6.15.
is it possible to switch the database component to something else? like an updated modern pervasive or sql database?
I am running on some performance & stability issues and would love to get on to some other database engine.
before you ask, the client is locked on P3 v3.1 and won’t upgrade to P6.
Thank you.
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?