linking of activites after retriving

Vijayendra SurveMember for 19 years 5 months
Created
1
2
0
sir,
for typical floors take 52 floors once we copy activities n fragnet links r there but after retreving if one of links needs to b changed is there any other way to do tht for all 52 floors by global change or something.
Also if i want to insert/merge activities (wth links) in revised progg. how should tht be done.

1 reply

Oldest first
  1. 0
    Mangesh Khuspe ·
    hi
    dear u better export that whole project to excel get it mofified there and import it back to p3.
    do such kinds of things in excel i generally do this way only.
    regards
    mangesh