Auto Link ???? (Multiple Activites to Same Successor)

Sami Abu al HeijaaMember for 20 years 1 month
Created
4
3
0
Hi All


Can any body tell me how to link multiple activites to the same successor , actulley I tried the Global Change but i could’nt make it


thanks

sami

4 replies

Oldest first
  1. 0
    Dayanidhi Dhandapany ·
    I think you can export the activities with successor information, then try to do the changes in Excel and import back to P3
  2. 0
    Sami Abu al Heijaa ·
    Dear Dayanidhi


    My problrm that these activites are not linked at all to any successo so I made a completion activity which i want to link them to thats it !! have you got the picture
    by the way it was a qustion too how can i export those info to excel



    thnx

    sami
  3. 0
    Hemanth Kumar ·
    I Persume You Want To Link A Group Of Activities To One Activity Or Milestone As Predecessers And You Dont Know Linking Data With Excel
    Try This

    First Link Manualy to One Predecessor
    Open The Activity Form
    Open Successor Form
    Select The Linked Activity ( From Group Of Activities )
    You Will See In the Form the ID of Successor
    Now Copy That Actvity ID

    Select another Activiity
    Paste Acivity ID in The Succsessor Form
    Click Another Activity
    Go On


  4. 0
    Ahmed Saudagar ·

    Sami

    As to import from Excel, you must create a DBF file with feilds of "ACT" as the first column where you list Activity IDs of all the activities to which you wish to add the common successor to. In the second column you must have "SUC" as the field data where you will fill the common completion Activity ID. In addition you must have Fields of "LAG" which must be ’0’ and ’REL’ which must be ’FS’ for all the activities.

    Regards

Log in or join to reply