Critical Path issues.

Kevin MatthewsMember for 20 years 3 months
Created
4
1
0
Hello All,

Is there a way to make the last activity non-critical. On a number of projects I have a critical path which includes the last few activities because they are last; and not really critical? (although I understand the logic that if they slipped the project would slip)

I have, for a work around, used project finish milestones and linked the last activity in the critical path to it to get around this (making the milestone the last activity.)

Is this the only way to get around this ?

Thanks in advance,

Kevin.

4 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Kevin

    As I understood, these activities don’t really belong to the project - e.g. warranty, later adjustments during operation...
    Some companies use different accounts for those activities and a different person will be responsible.
    In P3 you can create a project within the project group of your big projects. So you can put those activities into an extra project. It will have some advantages: e.g. clean project plan, proper critical- and longest path.

    Hope, this will help

    Dieter
  2. 0
    Zhang Haixiang ·
    Hi,
    there’s always a last activity, and always on critical path.

    if you don’t want to show it, just change the filter for critical path, add sth. like activity id <> XXXX
  3. 0
    Christian Adrian De Vera ·
    Kevin

    Logically if those activities doesn’t really drive the project then it shouldn’t be on the critical path, but then again you have to consider the intention of why you need to show those activities on the critical path. Ask yourself "Do I really need to show this?" if not then ask a senior in your project get another view.
  4. 0
    Paul Harris ·
    You could always set a Project Finish date in the Project overview form. Then the last dates are calculated from this date.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au

Log in or join to reply