P3 Project Restore Issues
In the Open Standard
Jared WilliamsMember for 17 years
- Created
- 16
- 3
0
Greetings,
First post, forgive me if this has been covered but atm the search function is down. I hope to make up for my questions with some answers to others.
I received a P3 backup file from a contractor and when I restore it all the files seem to be intact but P3 will not recognize it when trying to open. I tried the built in restore function, tried making it an exe file and restoring that way and even got the contractor to send me the files zipped and still I cant get it to open.
I have a feeling if I sat down at the contractor’s computer I could find something he did wrong in some setting... but am at a loss atm and dont want to keep asking for different version unless I can figure out for sure what the issue might be.
I did specifically ask he checked compress and remove access list, but basically it wont list the project in P3.
Also I tried a P6 import based on the P3 files and it will show the project but can not complete the import saying the file can not be opened.
Any help would be appreciated.
Jared
First post, forgive me if this has been covered but atm the search function is down. I hope to make up for my questions with some answers to others.
I received a P3 backup file from a contractor and when I restore it all the files seem to be intact but P3 will not recognize it when trying to open. I tried the built in restore function, tried making it an exe file and restoring that way and even got the contractor to send me the files zipped and still I cant get it to open.
I have a feeling if I sat down at the contractor’s computer I could find something he did wrong in some setting... but am at a loss atm and dont want to keep asking for different version unless I can figure out for sure what the issue might be.
I did specifically ask he checked compress and remove access list, but basically it wont list the project in P3.
Also I tried a P6 import based on the P3 files and it will show the project but can not complete the import saying the file can not be opened.
Any help would be appreciated.
Jared
16 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?